Vacuum excavation supporting highway safety improvements on M60
14th Aug 2025

Vacuum excavation is playing an important role in the National Highways Irwell Valley scheme where a VAC UK team is working alongside colleagues from Kilkern to facilitate the installation of a new concrete Delta Bloc safety barrier on the M60.
VAC UK has been brought to provide specialist vacuum excavation services including clearing more than 2km of cable troughs.
The works are part of a £3.7m National Highways scheme to replace the existing central reservation steel fence between Junction 16 (Clifton Interchange) and Junction 18 (Simister Island). The upgrade will improve safety for motorists by reducing the risk of crossover collisions and lowering long-term maintenance needs.
Vacuum excavation central to programme
Kilkern is delivering a phased programme of works in three phases:
- Phase 1 – Strengthening 19 manholes on night shifts to allow hard shoulder running.
- Phase 2 – Central reservation works: removing 2,100m of cable trough covers, vacuum excavating troughs, ST5 concrete infill, rotating 11 chambers, and installing CKD units ready for barrier installation.
- Phase 3 – Reinstating strengthened manholes with new covers and finishes.
VAC UK Director Patrick Curran said:
“This project showcases our ability to deliver multi-phase works in a live highway environment. By combining Kilkern’s civil engineering and highways expertise with VAC UK’s industry-leading vacuum excavation technology, we can ensure safety, precision, and programme certainty.”
“We’re proud to be working alongside main contractor Octavius and all stakeholders to deliver this important safety upgrade for the M60.”